|
LATOURELL CREEK BRIDGE

Location:
Spanning Latourell Creek on the Columbia River Highway, Latourell
vicinity, Multnomah County, Oregon UTM: Bridal Veil, Oregon
Quad. 10/561 125/5042925
Date of Construction:
1914
Structural Type:
Reinforced-concrete braced-spandrel deck arch
Engineer:
Samuel C. Lancaster, Consulting Engineer/Assistant Highway
Engineer
K.P. Billner, Resident Designer
Builder:
Pacific Bridge Company, Portland. Oregon
Owner:
Oregon Department of Transportation
Use:
Vehicular and pedestrian bridge
Significance:
Latourell Creek Bridge is a three-span reinforced concrete
braced-spandrel deck arch. The braced spandrel framing is
usually found only in steel deck arch construction, and is
unique to this structure. At the time of its construction
it was one of the lightest concrete bridges, relative to its
dimensions, in the country. This bridge established the essential
form of the concrete arch that would be used in Oregon and
other sections of the United States.
Project Information:
Documentation of the Latourell Creek Bridge is part of the
Oregon Historic Bridge Recording Project, conducted during
the summer of 1990 under the no-sponsorship of HABS/HAER and
the Oregon Department of Transportation. Researched and written
by Kenneth J. Guzowski, HAER Historian, 1990. Edited and transmitted
by Lola Bennett, HAER Historian, 1992.
LATOURELL CREEK BRIDGE
Samuel Lancaster, with bridge engineers
C.H. Purcell, K.P. Billner and L.W. Metzger, worked out the
designs for the numerous bridges along the Columbia River
Highway. They designed each bridge to conform to the unique
topography that existed at the construction sates. These structures
were designed to be light, graceful and durable as well as
innovative in their construction technique for the period.
The following passage helps to illustrate Lancaster's devotion
to his work on the Columbia River Highway. ''Lancaster had
a great and deep love for the beauty of the Cascades and the
Columbia, and had a talent bordering on inspiration for solving
difficult engineering problems.
Latourell Creek Bridge is one of eight
deck arches built on the Columbia River Highway between 1913
and 1921. This structure crosses the stream below Latourell
Falls. Originally, visitors could view the falls from the
bridge, but an overgrowth of vegetation presently obscures
the view. Joseph Latourell was a prominent citizen in the
area and the falls were named for him. ''Rooster Rock post
office was established in May. 1876. Joseph Latourell became
postmaster in August, 1876 and the name was changed to Latourell
Falls in August, 1887. The bridge is now located in the 220
acre Guy W. Talbot State Park, which was given to the state
of Oregon in early 1929 by the Talbot family.
This bridge was designed by K.P. Billner
who was the ''first American engineer to break entirely with
tradition and treat the concrete arch as a distinct kind of
structure comparable in its behavior to the elastic ribs of
steel" that had become popular in the late nineteenth
century. Historian Carl Condit believes that the Oregon State
Highway department played a leading role in the development
of American concrete bridges, with their earliest contributions
found on the Columbia River Highway.
DESIGN AND DESCRIPTION
The total length of the bridge is 316'
and the width is 25' including the 17 foot roadway and two
3 foot cantilevered sidewalk. This is a three-span reinforced
concrete braced-spandrel deck arch bridge, with three 80 foot
parabolic rib arches and two girder approach spans that are
30' And 40'. The arches are open spandrel with vertical columns
and diagonal members. Two 20- inch square arch ribs carry
each span. They are reinforced by eight longitudinal l-inch
square bars and No. 0000 hooping, 18" in diameter, with
a 2 inch pitch.
This rib reinforcing technique represents
an early departure from Joseph Melan's outmoded technique
of using parallel metal I-beams embedded in concrete. At the
turn of the century, the Melan system of reinforcing was popular
for concrete arches, although the more efficient methods of
bar reinforcing introduced by Ransone in 1889, were beginning
to gain new attention. By 1910, the main line of evolution
was moving away from massive construction, with its echoes
of the masonry tradition, toward the flattened parabolic curves
of narrow ribs, slender spandrel posts, and minimal piers
that scientific reinforcing was to make possible.
The deck load and superimposed load is
carried to the arch rings on vertical columns placed at 10
foot centers. To insure against bending moments from partial
loading in the arch ribs, diagonal members were erected between
the junction points of the arch ribs and the vertical columns;
and the deck and the columns. These diagonal members are subject
to alternating compressive and tensile stresses. Special care
was employed in the construction of the junction points. The
reinforcing bars of the diagonals are hooked around the longitudinal
reinforcement of the arch ribs and also around the longitudinal
reinforcement of the girders which form the edges of the deck.
Where it was impossible to hook the bars to one another as
describers special dowels were inserted in the hooks. The
joints received a rigid inspection during the erection of
the bridge.
The main piers are 97' high from stream
bed to deck. The concrete above ground amounted to 560 cubic
yards, making this one of the lightest concrete bridges, relative
to its dimensions, in the country. If the traditional ideas
of construction had been followed a bridge with the same strength
would have contained 1,200 cu. yd. of concrete. Because of
this innovation, there was a savings of $12,000 in concrete,
with a moderate increase in the cost of false work.
A light bridge was important at this sight
because of difficulty in securing a firm foundation. The underlying
bedrock is covered with a layer of silt and boulders to an
average depth of 25 feet on the western shore. On the east
side of the creek, there is a deposit of drift sand 50 feet
deep. At the east end, the bridge the bridge piers descend
56 feet into the ground. The cost of building abutments and
piers for a heavier type of bridge would have been considerable
with these foundation conditions to contend with. Safety factors
are as high on this bridge as any on the highway. At each
end of the bridge, there are two girders which carry a set
of columns and struts which support the roadway. Precast concrete
railings include balustrades with arched openings, caps and
posts. Curved brackets support the railing and impressions
of the narrow lath false work that was used in forming them
can be seen.
Latourell Creek Bridge is the only braced-spandrel
concrete arch on the State Highway System. Its spare, clean
and economical shape results in a lightness of structure akin
to that found in steel. The braced-spandrel framing is usually
found only in steal deck arch construction. The X-braced towers
carry the comparison to steel even further.
The west abutment and two central column
bents are placed directly on bedrock. The east abutment rests
on four columns, two 4" square, and two 5" square.
The average depth of these columns is 45 feet from the underside
of the abutment to rock. The tops of the five foot columns
are connected to the bases of the 4 foot columns by inclined
struts. The thrust from the arches is transmitted down to
the rock foundation.
The false work was erected with a tower
at each end of the bridge and an aerial cable-way stretched
between. All of the forms were constructed and braced before
the pouring of the concrete superstructure began. The main
columns were poured in afoot sections and allowed to solidify
for a few hours between the pourings. The arch ribs were poured
simultaneously, starting at the spring line and moving towards
the crown. The deck contains 250 cubic yards of concrete and
was poured in a continuous operation lasting twenty hours.
The men worked from 7 A.M. one day to 3 A.M. the next--only
a few of them stopping at one time for food. The maximum settlement
during the pouring of the arches was 3/8". The deck was
poured after the arches had set for twelve days. No settlement
took place while the deck was being poured or after. The false
work was struck six weeks after the pouring of the arches.
Wind stresses on the deck and balustrades
were taken care of by the rigid deck construction and transmitted
to the large abutments. The wind stresses on the bowstrings,
webbing and supports were taken up by diagonal counter braces.
Tension stresses were provided for by the hooks on the steel
bars which grip the rods of the connecting members. The concrete
was not intended to take tension stresses. The heavyweight
of the east abutment was calculated to give a horizontal reaction
equal to the maximum thrust of the bow strings. Expansion
joints were not installed because of the elastic, light, springy
design and the heavy reinforcements. Temperature stresses
were not a major consideration because this bridge was built
in an area where temperature is uniform with few variations.
The horizontal reaction caused by impact was assumed to reach
a limit of 30 tons. The unit stress in the deck from a reaction
of 30 tons was 25 lbs. per square inch. The concrete piles
carry 30 tons each.
Billner intended that this bridge be one
or the lightest concrete structures of its dimensions in this
country. He explains the method of construction in a 1915
article in Engineering and Contracting:
The thrust of the arches are transmitted
to the rock foundations by inclined struts, which connect
the tops of the 5 foot columns with the bottoms of the 4
foot ones. The vertical columns which carry the weight of
the deck and its superimposed load to the arch wings, have
a section of 14x12 ins. and are reinforced with four 3/4
in. round rods and with No.7 wire stays spaced 24 ins. on
centers. To provide against bending movements in the arch
ribs due to partial loadings 12x12 in. diagonal members
are inserted in each panel. These members are reinforced
with four 7/8 in. round rods and with No. 7 stays spaced
12 ins. on centers. Special care was used in the construction
of the end connections of these diagonal members, their
reinforcing bars being hooked around both the longitudinal
reinforcement of the arch ribs and that of the girders.
Where it was impossible to provide connections of this kind
special dowels were inserted in the hooks. The springing
points of the arches are restrained by making the main columns
serve as beams, by means of double reinforcement.
Reinforcing for this bridge was innovative
and moving away from the heavily reinforced bridges of the
period.
Bridge analysis in the summer of 1990 revealed
the presence of electrical conduit in the railing piers. Billners
correspondence explained: ''Regarding electric conduits or
iron pipes for electrification or the bridge at Latourell,
I do not know the difference in price of regular conduit and
that of pipe but the conduit would be preferable because of
the large quantities of steel in the bridge." The conduit
was installed but the lamp standards were never put in place.
The paving of the bridges was performed
by the Warren Construction Company. They specified in 1915:
All concrete floors to be swept as clean
as possible and apply over same a thin coating of asphaltic
cement not to exceed one-half gallon per square yard, and
on this paint coat there shall then be spread the bitulithic
wearing surface mixture, the same as that called for by
the Multnomah County specification for other work on the
Columbia River Highway, the pavement to be 18 feet in width
with 3 1/2 inch crown in the center and gradually tapered
to 2 inches at the gutter line. In the laying of bridge
pavement additional fussy work was involved since the bridge
floors needed to be crowned which was slow work, also requiring
special tamping at the gutter line.
Today the bridge has a slight crown to
the decks so it must be assumed that the surfacing work was
performed by the Warren Construction Company even though early
specifications called for no crown in the pouring of the deck.
In 191 5 Samuel Lancaster wrote this description of the bridge:
The falls at Latourell can be seen from
the bridge pouring their shining waters over the wall of basalt
cliff where the rock is formed into pentagonal shapes which
hang down like icicles. The Giant's Causeway of the Irish
Coast is well known, but it offers no better example of rock
crystallization. The roadway forms a suitable frame to the
beautiful picture and adds a charm to the landscape.
Today the trees are much taller and conceal
a considerable amount on the highway and bridge, creating
a forested effect that contrast with Lancaster's original
design intent for a tame and cultivated European landscape
along this highway. This bridge established the essential
form of the concrete arch that would be used in Oregon and
other sections of the United States.
REPAIR AND MAINTENANCE
Maintenance records from the Oregon State
Highway Department reveal that little maintenance was need
on the bridge until the 1930's when it became necessary to
repair broken hand rail spindles and damaged curbs on the
pedestrian walks. Late 1930's maintenance records explain
that the brush in the vicinity of the bridge needed to be
cleared. 1950's maintenance records mention that spalling
was occurring to the spindles on this bridge. By 1969, serious
spalling was evident on the spindles caused by moisture penetration
and expansion of the reinforcing bar. Replacement of the spindles
in kind in the early 1980's. The original precast spindles
were made by William P. Vrooman of Salem. Oregon.
Excerpted from Historic
American Engineering Record, Latourell Creek Bridge, HAER
0R-OR-24.
Researched and written by Kenneth J. Guzowski,
HAER Historian, 1990. Edited and transmitted by Lola Bennett,
HAER Historian, 1992
|